Ask your own question, for FREE!
Mathematics 40 Online
OpenStudy (anonymous):

28 men can finish the job in 60 days. At the start of the 16 day, 5 men were laid off and after the 45th, 10 more men were hired. How many days were delayed in finishing the job? Please explain, step by step.

OpenStudy (anonymous):

let eaceh man do x amount of work. so the total amount of work to be done is 28*x*60=1680x work done in first 15 days = 28*x*15 =420x work done in the next 30 days =23*x*30=690x remaining work = 1680-690-420=570x so remaining days = 570x/33x=17.27 so total days are 62.27 2.27 days excess

OpenStudy (anonymous):

a repeat yes?

OpenStudy (anonymous):

yes, i just wanted to see other possible solutions, but thanks to the both of you! :)

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
ARTSMART: Art!
1 hour ago 4 Replies 3 Medals
Jasonisyours: What were the key causes of the French Revolution in 1789?
2 hours ago 2 Replies 4 Medals
PureSoulless: Why is the word "Pedophile" always censored in yt vids?
23 hours ago 3 Replies 0 Medals
Jalli: What's 58x3634u00b07
19 hours ago 6 Replies 3 Medals
arriya: who wanna play roblox
1 day ago 5 Replies 1 Medal
brianagatica14: Any artist on here?
3 days ago 7 Replies 2 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!