28 men can finish the job in 60 days. At the start of the 16 day, 5 men were laid off and after the 45th, 10 more men were hired. How many days were delayed in finishing the job? Please explain, step by step.
Still Need Help?
Join the QuestionCove community and study together with friends!
let eaceh man do x amount of work. so the total amount of work to be done is 28*x*60=1680x work done in first 15 days = 28*x*15 =420x work done in the next 30 days =23*x*30=690x remaining work = 1680-690-420=570x so remaining days = 570x/33x=17.27 so total days are 62.27 2.27 days excess
a repeat yes?
yes, i just wanted to see other possible solutions, but thanks to the both of you! :)
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
22 hours ago
1 Reply
0 Medals
5 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
3 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal