John can do a piece of work in 8 days. If Paul can do it in 10 days, in how many days can both do it together? Please explain step by step (and explain) :D
Still Need Help?
Join the QuestionCove community and study together with friends!
john does 1/8th a pieace in a day, paul does 1/10 a piece in a day. the equation to solve is x((1/8)+(1/10))=1 where x is the number of days and it equals 1 because you're looking for a complete piece of work
and the answer is....ba badum dum....(insert dramatic music).....
x = 1/((1/8)+(1/10)) = 40/9
is it 40/9 or 4 (fraction bar) 4/9
40/9 = 4+(4/9) = 4.444
Still Need Help?
Join the QuestionCove community and study together with friends!
Thanks :D
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
15 hours ago
1 Reply
0 Medals
5 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
3 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal