A contractor employed 210 men to build a house in 60 days. After 12 days , he was joined by 70 more men. In how many days will the remaining work be finished.
Come on, 1/3 more men to finish 4/5 of work....
How many mandays the job takes?
if 210 men take 60 days then 280 men would take 210/280 * 60 = 45 days that is 280 take 3/4 of the time that 210 take and there are 48 days left if 210 do the work so how do you calculate how long 280 men would take?
the standard reply to any contracting job is: itll be finished in 2 weeks. :)
And at 10 days, u know, there's a bit of a problem.........
lol
her each man cando 1/60*280 part of job per day so 210 of them worked for 12 days and completed 12*210/60*210 =1/5 th part of the job now job ramaining is 4/5th they have 70men more and total of 280 let the number of days rquired be x then x*280/60*210=4/5 so x=180/5=36 so they take 36 more days to finish the work