OpenStudy (goldrush18):

hi everyone i need help with a business assignment its on Critical Path Analysis/Method is there some who can help me?

OpenStudy (anonymous):

whats the question?

OpenStudy (goldrush18):

red wise manufacturing company would like to assess the activities completion time of predecessors for building a new convention centre. these are outlined in the table below activities] immediate predecessor] duration(months) A - 3 B A 4 C A 6 D B 6 E B 4 F C 4 G D 6 H E,F 8 Required: draw a full timed network diagram to depict the information. identify the critical path calculate the EST and LFT for each activity , show these on network diagram and then transfer them to a table where you will also show the float on each non-critical activity.

OpenStudy (goldrush18):

i'm having a problem calculating the critical path because there is a dummy activity in the network diagram

OpenStudy (anonymous):

so wht is the problem with dummy?

OpenStudy (anonymous):

there are two situations when dummy appears.. 1. IF WE HAVE TWO ACTIVITIES HAVING SAME HEAD AND TAIL EVENT WITH DIFFERENT CONSUMPTION OF TIME THEN ALWAYS WE SHOULD INTRODUCE DUMMY RELATION. 2. IF ANY ACTIVITY APPEARS ATLEAST TWO TIMES IN PRECEDING COLUMN, I IN INDIVIDUAL AND II WITH OTHER ACTIVITY, THEN WE SHOULD INTRODUCE DUMMY.

OpenStudy (anonymous):

IN YOUR QUESTION I THINK THERE WOULD NOT BE ANY DUMMY ACTIVITY AS NEITHER OF TWO SITUATIONS ARE APPLICABLE

OpenStudy (goldrush18):

ok so what then would be the critical path?

OpenStudy (anonymous):

|dw:1319137378057:dw|

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!