A contractor employed 210 men to build a house in 60 days. After 12 days , he was joined by 70 more men. In how many days will the remaining work be finished.
Still Need Help?
Join the QuestionCove community and study together with friends!
in this case a house requires 210 * 60 man days to build after the first 12 days, 210 * 48 man days remain for the next 48 days, 280 people are building the house.
i have got it but could u explain a little more
(210 * 60) = (12 * 210) + (280 * x) solve for x
now i got it completely thnxx for ur help thanks very much
It isn't the best question in the world. There an ambiguity in the question.
Still Need Help?
Join the QuestionCove community and study together with friends!
i am in class 8 it was tough for me
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
1 day ago
1 Reply
0 Medals
6 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
3 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal