It takes an electrician 45 minutes to wire an office in a new office building that is being built. The electrician signed a contract to wire all offices on 6 floors of the new building. There are 50 offices on each floor. How many weeks should the electrician allow for this job if he works a standard work week (8 hours per day for 5 days a week)? Express the answer in decimal form rounded to the tenths place.

OpenStudy (anonymous):

45 x 6 x 50 = 13500 (minutes) ... time needed (in minutes) 8 x 60 x 5 = 2400 (minutes) ... time in typical work week (minutes) 13500 / 2400 = 5.625 (weeks) .

OpenStudy (anonymous):

Round to the nearest tenth would be 5.6 weeks

OpenStudy (anonymous):

thank you

OpenStudy (anonymous):

13, 500 min / 60 = 225 hrs 225 hrs/ 40 = 5.6 wks

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol: i need help
2 days ago 7 Replies 1 Medal
Arriyanalol: CONGRATS to me
2 days ago 8 Replies 2 Medals
Legomaster346: What colleges are good that are near Arab Alabama?
1 week ago 5 Replies 0 Medals
Arriyanalol: i need help
1 week ago 6 Replies 2 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!