A construction company will be fined for each day it is late completing its current project. the daily fine will be $4000 for the first day and will increase by $1000 each day. based on its budget, the company can only afford $60,000 in total ines. what is the maximum number of days it can be late? a. 10 days b. 8 days c. 12 days d. 5 days

OpenStudy (albert0898):

First Day = 4,000 2nd = 5,000 3rd = 6,000 4th = 7,000 5th = 8,000 6th = 9,000 7th = 10,000 8th = 11,000 9th = 12,000 10th = 13,000 11th = 14,000 12th = 15,000 b. 8 days As a shortcut you could just do 5 + 6 + 7 and so on until you reach a number close to (must be less though) or equal to 60.

OpenStudy (anonymous):

thank you. not a fan of word problems (:

OpenStudy (albert0898):

Anytime! Glad to help lol :3

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!