A can do a piece of work in 24 days. When he had worked for 4 days B joined him, if the work was completed in 16 days, in how many days B alone can finish the work?
Still Need Help?
Join the QuestionCove community and study together with friends!
How much A can do in 1 day?
work/24
Good, Let B and do the work in x days, then solve this equation for x \[ \frac{1}{6}+12 \left(\frac{1}{24}+\frac{1}{x}\right)=1\] x= 36 days
I GET 90
Do you know the right answer?
Still Need Help?
Join the QuestionCove community and study together with friends!
I DON4T KnOW IF they compleet it after or in 16days !!!! maybe your true th
acctualy the right unsewer is 96
ow so the 4 days is not included in those 16 days. So in my equation you have to multiply by 16 instead of 12.
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
1 hour ago
1 Reply
0 Medals
4 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
2 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal