OpenStudy (anonymous):

Person 1 can do a certain job in 21 minutes, and person 2 can do the same job in 28 minutes. When completing the job together, which expression would be used to represent the amount of work done by person 1? 21 1/21 x/21 21x

OpenStudy (anonymous):

Think of it as a distance problem. dist. = rate*time In this case dist. = 1 (One job). time is 21 min. so we have\[1=21r\] Rate is 1 job per 21 min. so we have \[r={1\over21}\]

OpenStudy (anonymous):

here's a question. How long would it take if both person one and two worked on the same house at the same rates as they are in the original problem?

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!