5 men are hired to complete a job. If an additional man is hired, the job can be completed 8 days earlier. Given that the number of days required to complete the job is inversely proportional to the number of men hired, find the number of additional men who must be hired in order for the job to be completed 28 days earlier.
Still Need Help?
Join the QuestionCove community and study together with friends!
5 men => n/5 days 6men => n/6 days n/5 - n/6 = n/30 days = 8days n = 240 by 5 men it will be finish it 48 days 28 days earlier = 20 days 240 /20 = 12 12 - 5 = 7 additional men
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
serenitystXrgazer:
Getting sent to anti gay christian covestion camp in a few weeks, any tips. guys i think im cooked.
Aubree:
Guys, what does love feel like? I've been getting a tight chest and when I talk to him my heart rate hangs out around 100-120 beats per min, and when he doe
thereneelg:
ok... anyone have advice?? ...I did Choir all throughout Middle school and have ALWAYS been put in Soprano those three years.
kamariana:
The Byzantine Procopius is known for (5 points) reconquering much of the old Roma
chuckD:
hellp!!! what does it mean to describe a scientist as skeptical Why is sceptical
DoltonCarlee:
So like do y'all know anything about the first world war?
thehearken:
anyone know how to explain this so its easier for me to understand? b(1)=2, b(n)=
1 hour ago
1 Reply
0 Medals
7 hours ago
10 Replies
2 Medals
2 days ago
6 Replies
1 Medal
3 days ago
0 Replies
0 Medals
3 days ago
2 Replies
1 Medal
2 days ago
2 Replies
0 Medals
2 days ago
5 Replies
2 Medals