Ask your own question, for FREE!
Mathematics 11 Online
OpenStudy (anonymous):

5 men are hired to complete a job. If an additional man is hired, the job can be completed 8 days earlier. Given that the number of days required to complete the job is inversely proportional to the number of men hired, find the number of additional men who must be hired in order for the job to be completed 28 days earlier.

OpenStudy (anonymous):

5 men => n/5 days 6men => n/6 days n/5 - n/6 = n/30 days = 8days n = 240 by 5 men it will be finish it 48 days 28 days earlier = 20 days 240 /20 = 12 12 - 5 = 7 additional men

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol: i need help
2 days ago 7 Replies 1 Medal
Arriyanalol: CONGRATS to me
2 days ago 8 Replies 2 Medals
Legomaster346: What colleges are good that are near Arab Alabama?
1 week ago 5 Replies 0 Medals
Arriyanalol: i need help
1 week ago 6 Replies 2 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!