5 men are hired to complete a job. If an additional man is hired, the job can be completed 8 days earlier. Given that the number of days required to complete the job is inversely proportional to the number of men hired, find the number of additional men who must be hired in order for the job to be completed 28 days earlier.
Still Need Help?
Join the QuestionCove community and study together with friends!
5 men => n/5 days 6men => n/6 days n/5 - n/6 = n/30 days = 8days n = 240 by 5 men it will be finish it 48 days 28 days earlier = 20 days 240 /20 = 12 12 - 5 = 7 additional men
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
9 hours ago
1 Reply
0 Medals
5 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
2 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal