The number of days needed to finish a quilt varies inversely as the number of people working on it. If it takes 15 days for three people to finish a quilt, how many people would be needed to finish it in 2.5 days? 0.5 18 12 20
Still Need Help?
Join the QuestionCove community and study together with friends!
y - days x - people y=k/x 15=k/3 => k=45 so equation is y =45/x 2,5=45/x => x=45/2,5 =18
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
15 hours ago
1 Reply
0 Medals
5 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
3 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal