An automobile maker has an order for 7,500 new cars to be delivered in one week. Each car must be fitted with a new hood ornament that requires 1 hour and 15 minutes to install. Assuming the factory operates on a standard workweek shift (8 hours per day for 5 days), how many workers must be assigned this job to meet the deadline?

OpenStudy (shane_b):

First you need to figure out the total number of man hours required to install the hood ornament on all 7500 cars...can you do that part?