It takes an electrician 45 minutes to wire an office in a new office building that is being built. The electrician signed a contract to wire all offices on 6 floors of the new building. There are 50 offices on each floor. How many weeks should the electrician allow for this job if he works a standard work week (8 hours per day for 5 days a week)? Express the answer in decimal form... need to know asap

OpenStudy (anonymous):

Total time in weeks = (45 min)(6)(50)(1 hour / 60 min)(1 week / 40 hours)