5. Thirty men take 20 days to complete a job working 9 hrs a day. How many hours a day should 40 Men work to complete the job?
Still Need Help?
Join the QuestionCove community and study together with friends!
How many hours is the job altogether?
You can use ratios. Do you know how?
please help on how to use the ratios
Takes 30*20*9 = 5400 hours to do the job So now u want 40 * 20 * x = 5400
Define ratios in your own words first, so that I can see that you know what it means?
Still Need Help?
Join the QuestionCove community and study together with friends!
Do you know what ratios are?
I am trying to teach you, not just get excited and give out answers like most do so if you don't know the reply to what I ask, then simply tell me.
Eg 30:20:9 and 40:20:w
Actually you don't need ratios. Do what estudier said above. That should work. Try it.
Calculus and estudier thank you
Still Need Help?
Join the QuestionCove community and study together with friends!
yw
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
1 day ago
1 Reply
0 Medals
5 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
3 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal