Ask your own question, for FREE!
Mathematics 24 Online
OpenStudy (anonymous):

A contractor employed 210 men to build a house in 60 days. After 12 days , he was joined by 70 more men. In how many days will the remaining work be finished.

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!