The number of days needed to finish a quilt varies inversely as the number of people working on it. If it takes 15 days for three people to finish a quilt, how many people would be needed to finish it in 2.5 days? Answer 0.5 18 12 20

OpenStudy (kira_yamato):

Let number of days = t, number of workers = x Since t and x are inversely related, tx = k, where k is constant of proportionality When t = 15, x = 3, k = 15(3) = 45 tx = 45 When t = 2.5, 2.5x = 45 x = 18

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol: i need help
2 days ago 7 Replies 1 Medal
Arriyanalol: CONGRATS to me
2 days ago 8 Replies 2 Medals
Legomaster346: What colleges are good that are near Arab Alabama?
1 week ago 5 Replies 0 Medals
Arriyanalol: i need help
1 week ago 6 Replies 2 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!