Say Frank can build a model airplane in 3 days, Jo can do it in 2, but Moe can only do it in 5 days. If they work together, they’ll build a model plane in: Possible Answers Selected Possible Answer 0.5 days 0.76 days 10 days 0.97 days 2 days
i think its 0.76 im not sure really i think its the rule of 3
a/b = c/x
nope its not 0.76 thats what i guessed.
would it be 2 days? since that is the fastest jo can do it
thats the best i can think of sorry
\[T_{F} = 3, T_{Jo} = 2, T_{Moe} = 5\]\[R_{F} = W/T_{F}, R_{Jo} = W/T_{Jo}, R_{M} = W/T_{M}\] W is work to be done to build a model airplane, R rate of work of wach person when three work together time taken \[W/(W/T_{F} +W/T_{Jo} +W/T_{M})\] 0.97 days
@sumanth4phy what formula is that? Rate = work / time? could you explain what you did there?
I see how you add their separate rates but why what are you dividing?
yeah Rate/Speed at which work is done = W/T I need time so T=W/R hence the division
OH gotcha riiight