At a processing plant, over the course of an 8-hour day, workers move material into a pile, which is removed at a constant rate by a conveyor belt. The workers move material into the pile at rate 600e^(−0.5t) units/hr while the conveyor belt removes the material at 150 units/hr. (a) At what time is the amount of material in the pile the largest and the smallest?