A contractor employed 210 men to build a house in 60 days. After 12 days , he was joined by 70 more men. In how many days will the remaining work be finished.

hero (hero):

So, what work have you done so far to figure this out?

OpenStudy (anonymous):

nothing

OpenStudy (anonymous):

please tell

hero (hero):

Hint: If it takes 210 men to complete the job in 60 days, then after 12 days, 1/5 of the job is complete. So 4/5 of the job remains to be completed.