A' and ' B ' can do a piece of work in 25 days and 30 days respectively. Both start the work together but ' A' leaves the work 8 days before its completion. Find the time in which the work is finished.
Still Need Help?
Join the QuestionCove community and study together with friends!
whats your attempt(progress) ?
1/25+1/30=a+b 's one days work (1-11/150)=(x-8)
A does 1/25 of the work in 1 day B does 1/30 of the work in 1 day together, in 1 day they do 1/25 + 1/30 of the work Let they both work together for x days then, they'll do x/25 + x/30 of the job after that, B does rest of the job alone for next 8 days => 8/30 of the work hence x/25 + x/30 = 1 -(8/30) = 22/30 solve for "x+8" . Hope it helps?
10 days.
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol:
@tinydinoUwU stop trying to find a argument u blad lil boy
TinydinoUwU:
**(Verse 1)** Yo, trapped in a box, Iu2019m feelin' so confined, Lifeu2019s a game of chess, but Iu2019m stuck in rewind, Every dayu2019s a struggle, man, I
Arriyanalol:
hey umm so i need help with my lanauage art ixl anybody wanna help big mama
Nina001:
ho where do i go to buy Subscirption for a moving pfp because on my screen im on
vain:
If the Admins and Mods are ever thinking about a new update for the site; I think what would be cool is that we add a "Profile Music" feature for our profil
Arriyanalol:
so i have a question reading time what is the long hand for then the short hand
10 hours ago
5 Replies
2 Medals
10 hours ago
12 Replies
4 Medals
3 days ago
2 Replies
1 Medal
4 days ago
4 Replies
2 Medals
4 days ago
17 Replies
1 Medal
5 days ago
0 Replies
0 Medals