If Andy and Billy work together, they can complete a project in 3.6 hours. If each of them works individually, Andy needs 3 hours less than Billy to complete the project. How long does Billy take to complete the project on his own?
Still Need Help?
Join the QuestionCove community and study together with friends!
\[{\rm Time =}\dfrac{ab}{a + b}\]U have \(a = b - 3\)
\[\dfrac{b(b - 3)}{b + b - 3} = 3.6\]solve?
b=1.2 or b=9 ?
those are correct values of b.
which value of 'b' you can eliminate ?
Still Need Help?
Join the QuestionCove community and study together with friends!
HINT: \(a = b -3\) but one of the \(a\)'s will be negative.
a=9-3=6 a=1.2-3=-1.8(rej.)
so i should get the answer a=6 and b=9. Therefore, Billy takes 9 hours to complete the project on his own. Right?
thats right
yes!
Still Need Help?
Join the QuestionCove community and study together with friends!
thanks
\(\huge \color{green}\checkmark\)
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
9 hours ago
0 Replies
0 Medals
4 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
1 day ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal