Alice can complete a project in 20 days and Bob can complete the same project in 30 days. Alice and Bob start working on the project together, with Alice quitting after some time, and it takes Bob another 10 days to complete the project. What is the total number of days it took to complete the project?

OpenStudy (amistre64):

what are the uit rates for each person?

OpenStudy (anonymous):

Alice = \[\frac{ 1 }{ 20 }\] Bob = \[\frac{ 1 }{ 30 }\] ???

OpenStudy (amistre64):

good, lets go ahead and figure out bobs 10 days of working

OpenStudy (amistre64):

are yo not interested in the results?

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol: i need help
18 hours ago 7 Replies 1 Medal
Arriyanalol: CONGRATS to me
21 hours ago 8 Replies 2 Medals
Legomaster346: What colleges are good that are near Arab Alabama?
1 week ago 5 Replies 0 Medals
Arriyanalol: i need help
1 week ago 6 Replies 2 Medals
Arizona: does anyone know the percentage rate of 30,000 and 40,000
1 week ago 0 Replies 0 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!