A company decides to set aside $100,000 for development of a new product. It estimates that development will cost $955 the first week and that expenses will increase by $65 each week. After 25 weeks, how much of the development budget will be left?

OpenStudy (tkhunny):

Week 1 955 Week 2 955 + 65 Week 3 955 + 65*2 Week 4 955 + 65*3 That looks like an Arithmetic Sequence. I wonder if there is a way to add up some finite number of those terms?

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol: i need help
18 hours ago 7 Replies 1 Medal
Arriyanalol: CONGRATS to me
20 hours ago 8 Replies 2 Medals
Legomaster346: What colleges are good that are near Arab Alabama?
1 week ago 5 Replies 0 Medals
Arriyanalol: i need help
1 week ago 6 Replies 2 Medals
Arizona: does anyone know the percentage rate of 30,000 and 40,000
1 week ago 0 Replies 0 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!