If 15 workers can pave 18 driveways in 24 days, how many days would it take 40 workers to pave 22 driveways? Please include a detailed explanation. Thank you.

OpenStudy (anonymous):

workers driveways days 15 18 24 1 18 24*15 1 1 24*15/18 40 1 24*15/(18*40) 40 22 24*15*22/(18*40)=11 11 Days Answer

OpenStudy (anonymous):

So basically we find the number of days if it's 1 worker and 1 driveway then put the number of workers and then the number of driveways we are required to find? BRILLIANT. Thank you so much!