30 people are working on a project. They plan to finish in 15 days. After working for 4 days, they add 3 more people to help. If each person works the same amount, how many days ahead of time can they finish the project?
Anyone?
ok you need to look at the avg rate each person is working at so if it takes 30 people 15 days to complete 100% of project, that is rate of 1/15 for 1 person it would take 30*15 = 450 days to complete project, that is rate of 1/450 now when 3 more people join the total rate of work increases to 33/450 rate * time = %project (work done) after 4 days --> (1/15)*4 = 4/15 of project is done leaving 11/15 left to finish now solve for time it takes 33 people to complete 11/15 of project --> (33/450)*time = 11/15 --> time = 10 so total time 10+4 = 14 , adding 3 people caused project to finish 1 day ahead of time
Great, thank you so much!!
yw