a contractor employed 210 men to build a house in 60 days after 12 days from start of the work he employed 70 more men. in how many days will the remaining work be finished?
Still Need Help?
Join the QuestionCove community and study together with friends!
did you get 16 as an answer?
16 is not the answer, sorry
i wasnt sure thats why i put a question mark to it. thanks for letting me know
60-12=48 210*48=280x 10080=280x divide both sides by 280 36=x
Looks like @sodukogirl13 has it
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
abby2blessed:
How do you guys feel about second chances? Concerning relationships, both romantic and otherwise.
TJH:
love Love, it comes, it goes But what if it stayed stayed in the silence the storm stayed when the world was loud for me it's different; it left when it was
Puffer:
General question what came first the chicken or the egg itu2019s a trick question
Bounty:
the world keeps moving fast and I'm stuck in a time lapse all I need is a minute
Bounty:
can I get so tips on how to start my journey into semi-realism art also on how to
Strawberryluna:
Read my poem. Im not for criticism its a poem I wrote after my breakup: Youu2019ll never understand the way you made me break, I hate that I still love you
Bounty:
first poem in a min- (tittle)? one moment i'm fine I smile till my face burns I laugh till I cant breath Then I cry I wonder where I went wrong I listen to
Twaylor:
3d printing a glider (for 150 pound 5'8 person - prolly should make it for up to
3 days ago
0 Replies
0 Medals
4 days ago
4 Replies
3 Medals
3 days ago
5 Replies
1 Medal
1 week ago
4 Replies
0 Medals
2 weeks ago
0 Replies
0 Medals
4 days ago
5 Replies
2 Medals
2 weeks ago
5 Replies
1 Medal
3 weeks ago
5 Replies
0 Medals