(Metals!!!!!) The time it takes to complete a job is inversely proportional to the number of workers. It takes 16 hours for 3 workers to complete a job. How long will it take 8 workers to complete the job? Show the work.
Still Need Help?
Join the QuestionCove community and study together with friends!
that only we need to do is cross multiply |dw:1387139507761:dw|
6 hours
@edolivera007 Are you sure it's the correct answer?
Because I get different answers.
yes oh what did you got i will tell u what you did wrong
Still Need Help?
Join the QuestionCove community and study together with friends!
I had 12 hours because you times the numbers.
i dont know how you got the answer but you only have 2 multiply 16 times 3 and the divide it by 8
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
20 hours ago
0 Replies
0 Medals
4 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
2 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal