For a driveway that is 32 feet wide, 12 yards long, and 9 inches thick, how many tons of Portland cement concrete is required if the unit weight of PCC is assumed to be 150pcf?
Still Need Help?
Join the QuestionCove community and study together with friends!
32*12*9 = 3456 so there's 3,456 cubed feet of cement needed. I'm assuming that is 150 pounds per 150 cubed feet so 3456 * 150 = 518400 there are 2000 pounds in a ton so... 518400/2000 = 259.2 you would need 259.2 tons of cement to fill the driveway
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
serenitystXrgazer:
Getting sent to anti gay christian covestion camp in a few weeks, any tips. guys i think im cooked.
Aubree:
Guys, what does love feel like? I've been getting a tight chest and when I talk to him my heart rate hangs out around 100-120 beats per min, and when he doe
thereneelg:
ok... anyone have advice?? ...I did Choir all throughout Middle school and have ALWAYS been put in Soprano those three years.
kamariana:
The Byzantine Procopius is known for (5 points) reconquering much of the old Roma
chuckD:
hellp!!! what does it mean to describe a scientist as skeptical Why is sceptical
DoltonCarlee:
So like do y'all know anything about the first world war?
thehearken:
anyone know how to explain this so its easier for me to understand? b(1)=2, b(n)=
2 hours ago
1 Reply
0 Medals
9 hours ago
10 Replies
2 Medals
2 days ago
6 Replies
1 Medal
3 days ago
0 Replies
0 Medals
3 days ago
2 Replies
1 Medal
2 days ago
2 Replies
0 Medals
2 days ago
5 Replies
2 Medals