A Librarian expansion begun in 2002 was expected to cost 107mill. the cost ended up being 44 mill over the budget. by what percent was the actual cost exceeded from the estimate
Still Need Help?
Join the QuestionCove community and study together with friends!
107*percentage = 107 + 44 percentage = (107 + 44)/107 = 1.411 1.411* 100 = 141.1 % , 41.1% over
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
22 hours ago
1 Reply
0 Medals
5 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
3 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal