If 18 identical machines required 40 days to complete a job, how many fewer days would have been required to do the job if 6 additional machines of the same type had been used from the beginning?
each machine has a rate of 1/(18*40). 6 more machines added, then 1/(18*40) = 1/(24 d) solve for d and d = 30 days. Which means it will take 10 fewer days
am not getting you.. any simple step...
well, what if 18 machines can finish the job in 40 days, then, in 40 days, each machine can do 1/18 job yes?
yes
got it now... :-) thanks...
ok, i'll finish: then in 1 day, each machine can do 1/(18 *40) job then in 1 day, 26 machines can do 26/(18*40) job which means it will take 26 machines 1/[26/(18*40)] = 30 days day, which means 10 days fewer
bundle of thanks dear... :-)