A pallet requires 2 minutes and 15 seconds to prepare for shipment, and 30 seconds to load on a trailer. How long will it take to prepare 40 pallets and load them onto a trailer
just multiply 40 into 30 seconds =1200 secs require to load them onto a trailer ... if u got it then click on best respoinse
@haseeb96 the question is "how long will it take to prepare and load 40 pallets" not just loading..
so for each pallet to prepare and load it takes 165 seconds to prepare=2min 15 sec=2*60 sec+15=120+15=135 to load=30 sec so total to prepare and load a pellet it takes 135+30 sec=165 sec
now calculate it for 40 pallets 40*165sec=6600 sec to convert into minutes divide it by 60 6600/60=110 minutes=1hr50 minutes
so it takes 1hr 50 minutes to prepare and load 40 pallets