25 men complete a work in 20 days 15 men leave after some days and the remaining work is completed in 37 1/2 days after how many days did the men leave
Still Need Help?
Join the QuestionCove community and study together with friends!
25 men can complete a work in 20 days that means number of `man days` required = 25x20
say those 15 men left ater \(\large n\) days : \[\large 25\times n + 10\times 37.5 = 25\times 20\] solve \(\large n\)
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
19 hours ago
0 Replies
0 Medals
4 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
2 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal