25 men complete a work in 20 days 15 men leave after some days and the remaining work is completed in 37 1/2 days after how many days did the men leave

ganeshie8 (ganeshie8):

25 men can complete a work in 20 days that means number of `man days` required = 25x20

ganeshie8 (ganeshie8):

say those 15 men left ater \(\large n\) days : \[\large 25\times n + 10\times 37.5 = 25\times 20\] solve \(\large n\)

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Latest Questions
Arriyanalol: i need help
1 day ago 7 Replies 1 Medal
Arriyanalol: CONGRATS to me
1 day ago 8 Replies 2 Medals
Legomaster346: What colleges are good that are near Arab Alabama?
1 week ago 5 Replies 0 Medals
Arriyanalol: i need help
1 week ago 6 Replies 2 Medals
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!