MEDAL even for HELP - If 1,000 units are required per year, which is least costly?
Alternative Resources Required
A Skilled Operator at $25 per hour; 35 minutes per unit of
skilled labor time
B Unskilled operator at $12 per hour plus automated
equipment costing $50,000; 10 minutes of operator time per unit
Still Need Help?
Join the QuestionCove community and study together with friends!
Sign Up
OpenStudy (greencat):
Where'd you get 35 from?
OpenStudy (adamaero):
min/unit
OpenStudy (greencat):
I don't quite get what you mean.
@satellite73
OpenStudy (greencat):
@HelpBlahBlahBlah
OpenStudy (greencat):
@mathstudent55
Still Need Help?
Join the QuestionCove community and study together with friends!
Sign Up
OpenStudy (adamaero):
Alternative B at $12/unit
Alternative A at $10.50/unit
I tried 35*1000 = 35000
35000/60 = num
num*25 = 14.583 (or 14.6 per unit)
$14.6/unit is wrong
What am I doing wrong?