During a recent rainstorm the basement of the police station was flooded. A pump was started, but after 2 hours it was decided that the process was taking too long. At that point a second pump was hooked up, and the job was completed using both pumps in another 3 hours. Working separately, it would have taken the original pump 4 hours longer than the new one. How long would it have taken the original pump?
Still Need Help?
Join the QuestionCove community and study together with friends!
Ok i THINK ITS 5.5 HOURS.
3/2=1.5+4=5.5
Thanks!
No problem^
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
13 hours ago
0 Replies
0 Medals
4 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
2 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal