During a construction project, engineers used explosives to excavate 140 feet of tunnel into a mountain. But because of time constraints and environmental concerns, they brought in a tunnel boring machine (TBM) to excavate the rest of the tunnel. The data table lists some observations an engineer made about the length of the tunnel after the TBM was introduced. How much of the tunnel was completed 26 days after the TBM was introduced? 1,170 feet 1,310 feet 1,260 feet 1,400 feet TBM Use (days) (feet) 6 410 15 815 20 1,040 28 1,400 33 1,625 38 1,850 45 2,165
Still Need Help?
Join the QuestionCove community and study together with friends!
20 days =1040 +6/8 of 360 because from 20 to 28 days 360 was excavated 26 days= 1040 +270=1310
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
heartlessprophet:
How do i get paid from work when im in job court ?
Aubree:
Guys, what does love feel like? I've been getting a tight chest and when I talk to him my heart rate hangs out around 100-120 beats per min, and when he doe
thereneelg:
ok... anyone have advice?? ...I did Choir all throughout Middle school and have ALWAYS been put in Soprano those three years.
kamariana:
The Byzantine Procopius is known for (5 points) reconquering much of the old Roma
chuckD:
hellp!!! what does it mean to describe a scientist as skeptical Why is sceptical
DoltonCarlee:
So like do y'all know anything about the first world war?
thehearken:
anyone know how to explain this so its easier for me to understand? b(1)=2, b(n)=
16 hours ago
0 Replies
0 Medals
18 hours ago
8 Replies
1 Medal
1 day ago
6 Replies
1 Medal
2 days ago
0 Replies
0 Medals
2 days ago
2 Replies
1 Medal
1 day ago
2 Replies
0 Medals
1 day ago
5 Replies
2 Medals