mike can complete a project in 60 minutes, and if mike and walter both work on the project, they can complete it in 40 minutes. how long will it take walter to complete the project by himself?
Still Need Help?
Join the QuestionCove community and study together with friends!
Mike =(1/60) project/min Walter =(w) project/min together (1 + 60 w)/60 project /min [(1+60 w)/60 ] 40 = 1 project 1 + 60 w = 6/4 60 w = .5 w = .0083333 1/w = min/project = 120 minutes
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
VERNEISH:
Two objects are moving along separate linear paths where each path is described by position, d, and time, t.
Maci:
what are the best stock apps for people who want to start investing?
Twaylor:
genuienly how do i get better self control i keep watcing youtube and theres this
IzzyCookie:
|dw:1792074056138:dw| Uhm, I don't know where to ask this, but I'm in college welding at my community college, and I need help learning vertical welding for
thehearken:
not sure if this is considered spam, im sorry if it is, but does anyone have tips
5 hours ago
1 Reply
0 Medals
4 days ago
3 Replies
2 Medals
1 week ago
3 Replies
0 Medals
2 days ago
9 Replies
1 Medal
1 week ago
2 Replies
1 Medal