please help three people who work full-time are to work together on a project, but their total time on the project is to be equivalent to that of only one person working full-time. if one of the people is budgeted for one-half of this time to the project and a second person for one-third of her time, what part oif the third worker's time should be budgeted to this project? A. 1/3 B.3/5 C. 1/6 D. 1/8

OpenStudy (anonymous):

C because 1/2 is 3/6 and 1/3 is 2/6 add thse together and u get 5/6 all u need left is 1/6 unless im reading incorrectly