@Tommynaiter
I think we are missing some information? We need to know how much it costs each hour.
Oh ok
The first Contractor start up fee is 200 and cost 50 each hour
The second Contractor start up fee is 150 and 55 each hour
The third contractor is 60$ each hour
So the first costs: \[200+50*210=10700\] And the 2nd costs: \[150+55*195=10876\] and the last costs: \[60*185=11100\] So here is the prices, they are very close, but contractor 3 is a bit faster, and since time is important the last contractor might be the correct.
So this is about arguing what is most important, saving some hours, or saving some money.
Saving money
Those are the total cost right?
Yes
The first is cheapest, but takes the longest time, and the last is the most expensive but takes the longest time. The middle is in between, so maybe that is an option? Then you get it kinda fast, and kinda cheap :)
The last is the most expensive but is the fastest**
B