Ask your own question, for FREE!
Mathematics 19 Online
OpenStudy (i_ask_alot):

If it takes 5 men 20 hours to brick a house, How long will it take 2 men to do the job if they work at the same rate ?

OpenStudy (i_ask_alot):

@welshfella please help

OpenStudy (welshfella):

It will take longer of course I fact by a factor of 5/2

OpenStudy (welshfella):

so its (20 * 5) / 2

OpenStudy (i_ask_alot):

so 50

OpenStudy (welshfella):

correct

OpenStudy (i_ask_alot):

Thank you so much.

OpenStudy (welshfella):

yw

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!