A manufacturing plant is going to use two different stamping machines to complete an order of 975 units. One produces 100 units per hour, while the other produces 75 units per hour. How long must each machine operate to complete the order if ,during the process, the faster machine is shut down for 25 hours for repairs? ( I just need help setting it up, thank you!)
Still Need Help?
Join the QuestionCove community and study together with friends!
let t = time operated by the slower machine then (t-2.5)= time operated by the faster machine : 75t + 100(t-2.5) = 975 75t + 100t - 250 = 975
175t = 975 + 250 175t = 1225 t = 1225/175 = t = 7 hrs by the slower machine and 7 - 2.5 = 4.5 hrs by the faster
thanks!
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
Aubree:
Guys, what does love feel like? I've been getting a tight chest and when I talk to him my heart rate hangs out around 100-120 beats per min, and when he doe
thereneelg:
ok... anyone have advice?? ...I did Choir all throughout Middle school and have ALWAYS been put in Soprano those three years.
kamariana:
The Byzantine Procopius is known for (5 points) reconquering much of the old Roma
chuckD:
hellp!!! what does it mean to describe a scientist as skeptical Why is sceptical
DoltonCarlee:
So like do y'all know anything about the first world war?
thehearken:
anyone know how to explain this so its easier for me to understand? b(1)=2, b(n)=
11 hours ago
8 Replies
1 Medal
1 day ago
6 Replies
1 Medal
2 days ago
0 Replies
0 Medals
2 days ago
2 Replies
1 Medal
1 day ago
2 Replies
0 Medals
1 day ago
5 Replies
2 Medals