A manufacturing plant is going to use two different stamping machines to complete an order of 975 units. One produces 100 units per hour, while the other produces 75 units per hour. How long must each machine operate to complete the order if ,during the process, the faster machine is shut down for 25 hours for repairs? ( I just need help setting it up, thank you!)
Still Need Help?
Join the QuestionCove community and study together with friends!
let t = time operated by the slower machine then (t-2.5)= time operated by the faster machine : 75t + 100(t-2.5) = 975 75t + 100t - 250 = 975
175t = 975 + 250 175t = 1225 t = 1225/175 = t = 7 hrs by the slower machine and 7 - 2.5 = 4.5 hrs by the faster
thanks!
Can't find your answer?
Make a FREE account and ask your own questions, OR help others and earn volunteer hours!
Join our real-time social learning platform and learn together with your friends!
Join our real-time social learning platform and learn together with your friends!
Latest Questions
abby2blessed:
How do you guys feel about second chances? Concerning relationships, both romantic and otherwise.
TJH:
love Love, it comes, it goes But what if it stayed stayed in the silence the storm stayed when the world was loud for me it's different; it left when it was
Puffer:
General question what came first the chicken or the egg itu2019s a trick question
Bounty:
the world keeps moving fast and I'm stuck in a time lapse all I need is a minute
Bounty:
can I get so tips on how to start my journey into semi-realism art also on how to
Strawberryluna:
Read my poem. Im not for criticism its a poem I wrote after my breakup: Youu2019ll never understand the way you made me break, I hate that I still love you
4 days ago
0 Replies
0 Medals
5 days ago
4 Replies
3 Medals
4 days ago
5 Replies
1 Medal
1 week ago
4 Replies
0 Medals
2 weeks ago
0 Replies
0 Medals
5 days ago
5 Replies
2 Medals