Your team has almost completed work on developing a system designed to track inventory at a grocery store. The client then sends an email asking if the system can also track employee work hours. This challenge is an example of A. Time and Budget constraints B. Determining user requirements C. Requirements Creep D. Technological Advances Please help I'm stuck

OpenStudy (bugman954):

C. Requirements Creep AKA Scope Creep. This is nearly universal in software projects, as the work is being developed and tested the client uncovers all of the exceptions they need it to process. This example is really out of scope because it is really a new unrelated project. One way to combat Scope Creep is to look a lot of examples of the current records, spreadsheets, notes, etc... . You will find many of the exceptional items that will come up recorded in a notes column or in the margins of the documents. These are often critical exceptions that need to be allowed for in the original specification.

Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!
Can't find your answer? Make a FREE account and ask your own questions, OR help others and earn volunteer hours!

Join our real-time social learning platform and learn together with your friends!