A company can produce as many as 50 mountain bikes and as many as 60 road bikes per day. It takes 4 hours of labor to produce a mountain bike and 5 hours of labor to produce a road bike. The company has at most 300 hours of labor available per day. Let x represent the number of mountain bikes per day and y represent the number of road bikes produced per day. Four of the constraints for this situation are x≥0 , y≥0 , x≤50 , and y≤60 . What is the other constraint for the situation?
@Vocaloid
@Elsa213
@Ultrilliam
@Vocaloid
I did some research and I found answer
THIS IS NOT MY ANSWER!!!! 1 mountain bike needs 4 hours of labor. 1 road bike needs 5 hours of labor. 50 x 4 = 200 60 x 5 = 300 If the company opts to make road bike the whole day. They can produce 60 road bikes out of the 300 hours of labor per day. If the company opts to make mountain bikes the whole day. They can produce 50 mountain bikes per day with excess hours of 100 which can be used to make 20 road bikes.