the time required to do the job varies inversely as the number of people working. it takes 5 hours for 7 bricklayers to build a park well. how long will it take 10 bricklayers to complete job?
With solution pls
Well as we can see it states t takes 5 hours for 7 bricklayers to build a park well. So multiply the 5 hours it takes by the 7 brick layers \[5\times7=35\] Divide 35 by (how long will it take 10 bricklayers to complete job) \[35\div10=3.5\] So it will take (3.5) hours for 10 bricklayers to complete the job.
@Pimalea Do you understand?
Yes, I appreciate it very muchbut can you pls do it like this
Yes pls
the time required to do the job varies inversely as the number of people working. time required note a ,,t" number of people working note ,,n" the t varies inversely as n so this is : \[t = \frac{ k }{ n }\] it takes 5 hours for 7 bricklayers to build a park so this will write it in this form \[5 = \frac{ k }{ 7 }\] do you can continue it now ?