Help por favoe :0 It takes Beth nine hours to tar a roof. Jose can tar the same roof in 13 hours. Find how long it would take them if they worked together.
multiply 9x13 and it should give u an answer how long
that was wrong :/
um Add
You cannot simply add or multiply the hours together. That is not how shared work problems work. If it takes Beth 9 hours to tar a roof, then she can (1/9) of the job per hour, right? So for (t) hours, she does (1/9)t work Same logic for Jose (1/13)t work. Their work will add up to 1 completed roof, so (1/9)t + (1/13)t = 1, solve for t
i dont understand... how come it isnt 9t and 13t?
work = rate*time it takes her 9 hours to tar a roof. every hour, she gets (1/9) of the whole job done. 9t would imply 9 roofs per hour.