Six boys or four men can complete a piece of work in 24days. In how many days will 3 boys and 10 men together complete the same piece of work?
1 boy = 1/6 of the job 1 man = 1/4 of the job 3(1/6) + 10(1/4) = K 1/K = time to complete
something along those lines
"six boys OR four men"... is that correctly expressed?
s
3(1/6) + 10(1/4) = K 1/2 + 5/2 = K 3 = K 24(1/3) = 8
@amistre64 do you agree with the wording of this problem? Using "or"?
it better be OR if it is AND you cannot do it
suppose you say Six boys AND four men can complete a piece of work in 24days for all you know the boys do all the work and the four men go out and drink beer all day
I've never seen a working together problem with "or" in it.
i see no issue with the use of "or" ; we are still able to define the rate of a boy or a man with the information given: 4m = 1 job = 24 days m = 1/4 job = 6 days worth of work 6b = 1 job = 24 days b = 1/6 job = 4 days worth of work
10(6) + 3(4) = 72 days of work packed into the job; which is 3 jobs worth
they are working 3 times as fast, therefore a 24 day job is done in 1/3 the time
i got it.see 10/96+3/144=8
thatll work too :)
then wat ur trying to say
i said what i was trying to say ... i was reasoning thru the process
means
grt @amistre64
wat r u doing now
@amistre64 @satellite73
thats a fine method too :)
It's @satellite73 method. He still hasn't told me whether or not he's the originator of that setup.
i heard he got it from some guy in Sparta ...
but i just cant trust the voices in my head lol
I see you still got jokes.
grt all who replied my question
good luck anala :)
not only did i invent it, but i copyrighted it as well, and get a royalty every time it is used my invoice is in the mail
Awesome :) Share the wealth please.
kk
hey how m=2.4
Good question.
b and m represent something other than number of boys and number of men. I admit I didn't define it well.
3 is the number of boys and 10 is the number of men.
Actually @amistre64
Let me post another solution I think is correct.
b = 4 m = 6 \[\frac{(3b)(10m)}{3b + 10m} = x\] \[\frac{(12)(60)}{12 + 60} = 10\]
b = days each boy worked m = days each man worked
The solution I posted earlier...there was a fundamental flaw in it. I computed the wrong number the first time.
If it's wrong, please at least explain why it is wrong.
I think I'm beginning to see why it is wrong.
There's no way 3 boys can complete the work in 12 days. That would be faster than it takes the six to complete in 24 days.
:(
Maybe I'm looking at it the wrong way. Maybe the 3 boys could only do 12 total days worth of work because there are only three boys.
it takes 24 days for 6 boys to complete 1 job; it takes 1 day for 6 boys to complete 1/24 of the job; each boy does 1/6 of 1/24 of a job in 1 day; b = 1/144 of the job per day it takes 24 days for 4 men to complete 1 job; it takes 1 day for 4 mens to complete 1/24 of the job; each man does 1/4 of 1/24 of a job in 1 day; m = 1/96 of the job per day
3(1/144) + 10(1/96) is the amount of work done in 1 day
1/8 of the work is done in 1 day; therefore it takes 8 days to do one job
Well my alternative method attempts have failed.
i think inverse proportions are involved with this. That's why you used k as the variable.
you are not calculating the appropriate b,m,workday ratio is all
I solved enough working together problems to know that there's alternative ways to solve them.
there are :)
I'll figure it out. Thanks for the extra tips.
youre welcome
Join our real-time social learning platform and learn together with your friends!